June update on Team 2100 Towpath work

*Update June 2022*

Works have now started at Barnes. Works are due to be completed in August and all of the equipment will be removed from the site by the end of September 2022. In order to limit our impact on the park we will return the compound area and return the park to its current state.

Now that the works have started, it will require the temporary closure of parking bays from the week commencing 27 June 2022, to provide a safe working space during culvert works. Please note that the temporary closure of parking bays will be needed intermittently throughout the works until project completion in late September 2022. Any new information regarding the use of parking bays will be uploaded onto the project website. Please see roads in which parking bays will be temporarily closed intermittently below:
• Elm Bank Gardens
• Railway Side
• White Hart Lane

We will require parking suspensions in the locations of MH1 & MH2 in Elm Bank Gardens MH3 in Railway Side and MH5 to MH9 in White Hart Lane as per the drawings below:

Website link: https://consult.environment-agency.gov.uk/ksles/team2100-barnes-and-mortlake-project/

For further information about the TEAM2100 programme, please visit this website: https://www.gov.uk/government/news/thames-estuary-asset-management-2100-programme-team2100.